President Obama's Cincinnati bridge visit is an attempt to literally and figuratively connect Mitch McConnell and John Boehner. No word on whether the top two Republicans in Congress will show up, but Louisville Mayor Greg Fischer is reportedly going to pop in.
Somewhat of an agreement, anyway. Mallory said that the city and Duke will go before a judge in Common Pleas court, who will make the final decision as to who should pay for the utility relocation. According to the agreement, Duke Energy will begin moving its utilities in the next few weeks, and the court decision will determine cost responsibility later. The city and Duke are expected to file in Common Pleas court within the next few weeks, although the court decision could take years to finalize.
Roxanne Qualls, city council member and Democratic mayoral candidate, has long been a supporter of the streetcar project, which she values as an indispensable economic investment for the city of Cincinnati. Yesterday, Qualls announced her request for the city to ramp up the streetcar construction timeline in order to have the project completed in time for the All-Star Games, which will take place in Cincinnati July 2015. Her announcement came just weeks after the city revised its timetable to delay project completion until April 2016.
In a letter from Qualls to Mallory and Dohoney, she explains: “This may present a
challenge, but it is one I am sure the administration is capable of
meeting. The streetcar will serve a critical role in efficiently and
effectively moving visitors to and from Great American Ballpark and
allowing them to conveniently visit other venues such as Fountain
Square, Horseshoe Casino, Over-the-Rhine, Washington Park, etc.”
At the meeting, Mallory announced that the city would shoot for construction to be completed prior to the games, but there were no guarantees. The streetcar builder will ultimately set the timeline for the project, according to Jason Barron, Mallory's director of public affairs.
CityBeat recently covered the streetcar project's delays and how the 2013 mayoral race could affect its progress here.
Cincinnati City Council plans to move $29 million in funds to avoid further delays for the streetcar
project, but the city is still looking at a 2015 opening date. City officials announced Wednesday that a council
committee will vote Monday on three pieces of legislation to keep the
$110 million project in line with the recently announced delayed opening.
One measure would front $15 million to help Duke Energy move underground utility lines from the path of the proposed streetcar route. That money comes from the recent $37 million sale of land near the former Blue Ash Airport.
The city thinks it will get this money back once a dispute with Duke is resolved. The city contends that Duke is responsible for moving the lines, which the utility estimates will cost $18.7 million. Duke counters that the lines only have to be moved because of the streetcar construction, so the city should foot the bill.
“We’re fronting money for the Duke work until we can work out who pays for it with Duke,” city spokeswoman Meg Oldberding said. “It’s to keep the project on time and on budget. Delays would escalate the cost.”
Another ordinance would change the municipal code to “confirm the city’s existing rights” and clarify that utilities pay for the cost of relocating facilities unless otherwise negotiated, according to a news release.
Oldberding said Cincinnati has always maintained that it is the utility’s responsibility to relocate their facilities, so it is not a change in the city’s position.
The final ordinance would change the funding source that is repaying $25 million in bonds sold as part of the original plan to fund the streetcar.
Those bonds were originally being repaid with money coming into city coffers from southern downtown and the riverfront area.
That area wasn’t bringing in as much cash as expected, so the ordinance would have $14 million of the bonds repaid from a 1995 fund set up to collect service payments from the Westin/Star, Hyatt and Saks.
Oldberding said once the downtown district rebounds — it includes the Banks and the casino — it would repay the other fund.
The ordinances would not add to the project’s cost. Construction is scheduled to begin early next year.
Here's how The Enquirer describes an Ohio Supreme Court decision allowing Democrats to challenge a ridiculous Republican attempt to unfairly redraw Congressional districts: “Court ruling throws 2012 elections into chaos.” Here's the same report by WLWT, minus the drama: “Ohio Supreme Court Allows Redistricting Challenge.”