City Considering Around-the-Clock Work on Streetcar

Project executive says third shift would help minimize disruptions to public and traffic

Officials working on the $133 million streetcar project are considering taking up extra shifts to speed up delivery of new rail and minimize disruptions caused by construction, project executive John Deatrick told CityBeat on Friday.

If it goes as planned, the extra shifts would reduce the time needed to deliver and install rails around Findlay Market and Liberty Street from one week to a couple days at each location. That would allow the city to avoid closing down surrounding streets for more than a weekend or a Monday and Tuesday, according to Deatrick.

“The main reason isn’t to speed it up,” he says. “The main reason is it would minimize the impact on the motoring public, walking public and biking public.”

Deatrick insists the move is absolutely not related to recent election results that have called the project’s survival into question.

One of Mayor-elect John Cranley’s top priorities upon taking office in December is canceling the streetcar project, which he says isn’t worth the cost and the wrong priority for Cincinnati. He says the outgoing city administration is continuing construction of the streetcar in “a political manner” and running up the bill to make canceling the project more difficult.

But Deatrick claims the 24-hour shifts won’t add much in the way of new costs. He says contractors currently bill the city about $1.5 million each month and that should continue into the future.

As of September, the city had already spent $23 million and contractually obligated another $94 million to the project. The obligations, along with the threat of litigation from contractors involved in the project and taxpayers and businesses along the streetcar track,

have raised concerns about how much canceling the project would cost

— and whether it’s even financially prudent at this point.