City Manager Defends Streetcar Project

Council meeting covers streetcar's costs, benefits

Convening in packed City Council chambers today, Cincinnati officials discussed the costs and benefits of the streetcar project in light of a $17.4 million budget gap revealed by the city administration on April 16. City Manager Milton Dohoney Jr. said the project could and should be saved, but a minority of public speakers and some City Council members did not seem convinced.

To balance the budget gap, Dohoney said the city would have to pull funds from multiple sources. He said he will offer specifics in writing tomorrow, which invoked verbal disappointment from officials who were expecting details at the meeting.

“I'm disappointed in this presentation,” said Councilman Chris Smitherman. “We're here today to hear how we're going to pay for it.”

The meeting, which was called by Democratic Vice Mayor Roxanne Qualls shortly after the budget shortfall was announced, covered a presentation from Dohoney, comments from public speakers and City Council questions to Dohoney. Despite expectations prior to the meeting, no specifics were given for closing the budget gap even after extensive questioning.

Dohoney did reveal the price tag for halting the streetcar project: $72 million. According to Dohoney, the project has already cost the city $19.7 million, and the city would have to spend another $14.2 million in close-out costs. Another $38.1 million in federal grants would have to be returned to the federal government.

Dohoney added that terminating the project would also reduce faith in Cincinnati’s competitiveness and ability to take on big development projects.

The budget gap was originally $22.7 million, but the city administration identified $5.3 million in potential cuts. Dohoney said further cuts would “alter the scope” of the project and push it into a “danger zone.”

The budget gap is a result of construction bids coming in $26 million to $43 million over budget. The lowest bid from Messer Construction, which came in $26 million over budget, has already expired, but Dohoney said the company is still willing to work on the streetcar project.

The city could rework the request for proposal for construction bids, but Dohoney said city officials and third-party experts agreed it’s unlikely that would effectively lower costs.

Throughout the meeting, streetcar opponents argued that the cost of the project is too high and the budget shortfall is proof the program is unsustainable.

Most of Dohoney’s presentation focused on the streetcar’s purpose. He said the streetcar would help drive economic and population growth, which would then bring in more tax revenue to help balance the city’s operating budget. That would represent a turnaround for Cincinnati, which has been steadily losing population since the 1950s during a period that has coincided with disinvestment, urban flight and the dissolution of the city’s old streetcar system.

Throughout his presentation, Dohoney cited multiple examples and studies that found streetcars can help grow local economies. He said the city has not pursued the streetcar because “it’s a cool thing to do,” but because it follows the expert advice given to city officials about what’s necessary to compete with other cities.

Dohoney’s argument was previously supported by HDR, which the city hired to do an economic impact study in 2007. HDR found major benefits to connecting Over-the-Rhine and the Central Business District, including travel cost savings, increased mobility for low-income individuals and economic development that would spur rising property values. The HDR study was entirely supported and echoed by a follow-up assessment from the University of Cincinnati.

Some critics have argued that the study is outdated because it was conducted before Over-the-Rhine’s recent revitalization, but Dohoney said there are still several hundred vacant buildings in the area, particularly north of Liberty Street.

The project has faced continued opposition from Democratic mayoral candidate John Cranley, Republicans and the conservative Coalition Opposed to Additional Spending and Taxes (COAST). They say the project is too expensive and they’re skeptical of the economic growth being promised by city officials.

Opponents of the streetcar have so far put the project on the ballot twice, but Cincinnati voters rejected the referendum efforts. Still, the streetcar may be on the ballot again this year through the 2013 mayoral race between Democrats Cranley and Qualls (“Back on the Ballot,” issue of Jan. 23). Cranley opposes the streetcar, while Qualls supports it.

The streetcar project was originally supposed to receive $52 million in federal funds through the state government, but Republican Gov. John Kasich pulled the funds after he unseated Democratic Gov. Ted Strickland.

Beyond the financial cost, Dohoney pointed out Kasich’s decision raised concerns about the project’s feasibility among previous supporters, leading to more hurdles and delays. He said Duke Energy in particular began stalling efforts to move utility lines to accommodate for streetcar tracks because the company grew weary of the project’s prospects.

Duke’s reluctance led to a conflict with the city over who has to pay to move utility lines — a conflict Duke and the city agreed to resolve in court. While the court battles play out, the city set aside $15 million from the Blue Ash Airport deal to move utility lines, but city officials say they will get that money back if the courts side with the city.

The city originally expected $31 million in private funding for the streetcar project, but those expectations were dampened as a result of the Great Recession, which forced local companies to scale back private donations.

John Deatrick, the current project manager for The Banks, previously told CityBeat that it’s normal for large projects to deal with multiple hurdles. Deatrick, who the city wants to hire to manage the streetcar project, said, “Any time you try to build something — even out in the middle of a corn field — you’re going to have unexpected, unanticipated issues. ... These things happen, and that’s what project management is all about.”

Dohoney said the current phase of the streetcar project is only a starter line between Over-the-Rhine and Cincinnati’s business district, but city officials are already planning for a second line that would run up to the University of Cincinnati and hospitals in uptown. If Dohoney’s vision for the project were completed, streetcars would run on multiple lines all around the city, ranging from the Cincinnati Zoo to The Banks.

The streetcar budget debate comes amid another debate regarding a $35 million deficit in the city’s operating budget. Some streetcar opponents have tried to link the two issues, but the streetcar is funded through the capital budget, which cannot be used to balance the operating budget because of legal and traditional constraints.