Streetcar Supporters Launch Campaign to Save Project

Residents, business owners rally to lobby new mayor and council

Dozens of residents and business owners gathered in Over-the-Rhine on Tuesday to launch a campaign that seeks to persuade Mayor-elect John Cranley and the newly elected City Council to support the $133 million streetcar project.

Attendees included Ryan Messer, who used his life savings to renovate his home in Over-the-Rhine; Derek Bauman, co-chair of Cincinnatians for Progress; Jean-Francois Flechet, owner of the Taste of Belgium; and Derek dos Anjos, owner of The Anchor.

“We’re here today to keep the conversation going outside of political rhetoric and partisan politics,” Messer said. “Simply put, the streetcar is a component of Cincinnati economic development, and it’s a project that grows the whole city — not just an urban core, which, by the way, is an important part of developing this region.”

The group intends to lobby Cranley and the newly elected council, which appear poised to cancel the project when they take office in December.

At least three of nine elected council members — P.G. Sittenfeld, David Mann and Kevin Flynn — have told media outlets that they want a full accounting of the project before making a final decision. Another three — Chris Seelbach, Yvette Simpson and Wendell Young — are on the record as supporting the project. The final three — Christopher Smitherman, Charlie Winburn and Amy Murray — adamantly opposed the project in the past.

Members of the pro-streetcar group invited Cranley and all elected council members to join them at a town hall-style meeting on Nov. 14 at the Mercantile Library, where supporters will discuss their path forward. So far, supporters have publicly discussed a concerted lobbying effort, a referendum if council passes an ordinance undoing the streetcar project and possible legal action.

As CityBeat first uncovered, the costs of canceling the project

are currently unknown

, and some of the costs could actually fall on the operating budget that pays for police, firefighters and human services instead of the capital budget that is currently financing the streetcar project.

Much of the uncertainty falls on ongoing construction for the streetcar, which has continued despite the newly elected city government’s intent to stop the project. As of September, the city spent $23 million on the project and contractually obligated $94 million, some of which city officials say will need to be paid back even if the project were canceled.

The U.S. Department of Transportation also told city officials in a June 19 letter that nearly $41 million of nearly $45 million in federal grants would need to be returned if the project were terminated.

Supporters also claim Cincinnati would be giving up a 2.7-to-1 return on investment over 35 years if the city abandoned the streetcar now. That estimate is derived from a 2007 study conducted by consulting firm HDR, which was evaluated and supported by the University of Cincinnati.

Project executive John Deatrick says the HDR study is now outdated and the city is working on updating the numbers. Still, Deatrick says the project is intended to spur economic development, not just provide another form of public transportation.

The Nov. 13 issue of CityBeat will give a more in-depth look at the campaign to save the streetcar and some of the people involved in the movement.