City Manager Proposes Streetcar Budget Fixes

Recommendations would pull capital funding from multiple sources

City Manager Milton Dohoney Jr.
City Manager Milton Dohoney Jr.

City Manager Milton Dohoney Jr. released a memo yesterday detailing how the streetcar project's $17.4 million budget gap could be fixed by pulling funds from various capital projects and issuing more debt, upholding a promise he made at a contentious City Council meeting Monday.

The five-page memo says none of the proposed capital funding sources can be used to balance the city's $35 million operating budget deficit because of limits established in state law, which means the streetcar project is not being saved at the expense of cops, firefighters and other city employees being laid off to balance the operating budget.

"Neither Capital nor TIF funds can be used to help with the operating budget deficit that the City is facing," the memo reads. "They are separate sources of funds and by State Law, cannot be used for operating expenses like police and fire personnel."

At least $5.4 million would be temporarily pulled from the $10.6 million planned for the Music Hall renovation project, but the redirected Music Hall funds would eventually come back in capital budgets for fiscal years 2017, 2018 and 2019. City spokesperson Meg Olberding explained in an email that moving funds around would not hinder the Music Hall project.

"The use of $5.4 million of Funds set aside for Music Hall this year is money currently sitting in a fund for this year that will not be needed this year," she wrote. "Funds for Music Hall will not be needed until 2016, the agreed upon deadline for fundraising for the Music Hall renovation with the Music Hall Revitalization Company. Therefore, the City is still keeping its commitment to Music Hall, while also advancing the streetcar project."

About $6.5 million would be taken from infrastructure projects surrounding the Horseshoe Casino, including funds that would otherwise go to lighting the trees along Reading Road and a study that would look at adding a turn lane from Reading Road. The memo acknowledges the trade-off, but it also justifies the redirected spending: "However, since the Streetcar passes within two blocks of the Casino Site, it is a project within the Casino Area that both benefits the TIF District and the Casino."

The memo also recommends pulling $400,000 that was originally set for traffic signal replacement, which would be used for the traffic replacement component of the streetcar project.

Another $500,000 would come from funding currently set for water main relocation and replacement. The memo says the water main funding is simply Water Works' share: "Of the $21.7 million cost overrun for the Streetcar project, approximately $1 million was for water main relocation (and) replacement work. Water Works' share of this is $0.5 million."

The remaining $4.6 million would come from the city issuing general capital debt, which would be paid back through a small portion of the income tax that is established in the City Charter for permanent improvement purposes. The memo acknowledges this would cost other economic development and housing projects $340,000 a year over the next 20 years, but it claims the funding is justified because the streetcar project is a permanent improvement project.

The memo outlines other vague capital funding options that could be used to balance the budget, but Dohoney does not explicitly recommend them.

The memo also leaves open the possibility of future sources of funding, including $15 million that could be opened up if the city prevails in court against Duke Energy over who has to pay for moving utility lines to accommodate streetcar tracks — but this was money that was originally supposed to go to neighborhood development projects — and the sale of remaining city-owned land at the Blue Ash Airport.

City Council still has to consider and approve the memo's recommendations for them to become law.