Streetcar Audit Finds High Costs to Cancel

Operating costs also lower than previously projected

Cincinnati would save just $7.8-$52.6 million in capital costs if it incurs tens of millions in additional expenditures to cancel the $132.8 million streetcar project, according to an audit from consulting firm KPMG released Wednesday.

By showing the potentially high costs of cancellation, the numbers could throw a lifeline to the streetcar project just one day before City Council decides whether to restart construction or permanently halt the project.

But Mayor John Cranley appears undeterred in his commitment to cancel the streetcar project. By accounting for the annual costs to operate the streetcar, Cranley estimates the city will actually save $102 million if it cancels the project.

The city already spent roughly $34 million on the project, according to the audit. Cancellation would add $16.3-$46.1 million in close-out costs, bringing the total costs of cancellation and money spent so far to $50.3-$80.1 million.

Completing the project would add $68.9 million in costs, after deducting $40.9 million in remaining federal grants, the audit found.

But the completion estimate assumes the city will need to pay $15 million in utility work — a cost that is currently being debated in court. If the city wins its case against Duke Energy, the utility company would be required to pay the $15 million and bring down the total completion costs to $53.9 million.

The audit also put the costs of operating the streetcar at $3.13-$3.54 million a year, lower than the previous $3.4-$4.5 million estimate. After revenues from fares, sponsorships and other sources, the city would need to pay $1.88-$2.44 million to operate the streetcar, according to the audit.

The reduced estimate for operating costs could become particularly important in deciding the project's fate as private contributors attempt to get the cost off the city's operating budget.

Delaying the streetcar project while KPMG conducted its audit also added $1.7-$2.8 million in costs, according to the audit. The city allocated another $250,000 to pay KPMG for its work.

The audit did not account for the potential costs of litigation if contractors and investors along the planned streetcar line sue the city to recoup costs.

City Council paused the streetcar project on Dec. 4 to obtain the cost estimates of completion, cancellation and annual operations. The full body of council will decide whether to restart the project on Thursday, before a Friday deadline set by the Federal Transit Administration for federal grants.