Streetcar Project Executive John Deatrick on Nov. 21 revealed that the city might only keep $7.5-$24.5 million if it cancels the $132.8 million streetcar project.
That means the city could potentially spend more than 94 percent of the project’s total costs before it manages to fully close down the streetcar project, which is currently undergoing construction and tied up to various federal grants and business contracts.
The presentation was given in advance of Mayor-elect John Cranley and the newly elected City Council taking office in December. Cranley is an ardent opponent of the streetcar project, and a majority of council says it wants to pause the project and consider cancellation.
Cranley’s proposed alternative to the streetcar — a trolley bus system — would cost $10-$15 million in capital funds, according to supporters of the rubber-tire trolley alternative. If streetcar cancellation costs were to reach the high end of the city’s estimate and the trolley bus is paid for, the city could end up spending $140.3 million to cancel the streetcar project and build a less ambitious trolley bus line — about $7.5 million more than it would cost to simply complete the streetcar project.
If it’s completed, Cincinnati Budget Director Lea Eriksen says operating the streetcar would cost between $3.4-$4.5 million each year, which city officials say could come from various potential sources, including a special improvement district that would raise property taxes within three blocks of the streetcar route.
But the operating budget cost would be a wash if Cranley pursues the trolley bus system, which, according to advocates, will cost slightly more to operate than the streetcar. Cranley says the operating cost for the trolley bus is concerning if it holds true.
Following Deatrick’s presentation, Cranley held a press conference in which he flatly disputed the current city administration’s estimates. He says he will tap new experts to go over the numbers while the project is put on pause.
Deatrick’s cancellation projections account for $32.8 million in estimated sunk costs through November and a potential range of $30.6-$47.6 million in close-out costs, which include construction to close the project — such as repaving torn-up roads — and orders on vehicles and other supplies that are already placed but not officially billed.
The federal government has also allocated $44.9 million in federal grants to the streetcar project. In a letter released by the city administration on Nov. 14, the Federal Transit Administration (FTA) explicitly stated that $40.9 million would be taken back if the project didn’t adequately progress; the remaining $4 million would be left under the supervision of Gov. John Kasich, who could shift the money to other parts of the state.
But Deatrick’s estimates don’t account for potential litigation from contractors and taxpayers and the damage to Cincinnati’s image.
Three elected council members already support the streetcar project, so only two of the three potential swing votes — P.G. Sittenfeld, David Mann and Kevin Flynn — would need to vote in favor of it to keep it going.